Final four-mile HS2 tunnel dig to Euston from Old Oak Common to start 'very soon'
This marks the last major tunnelling phase of the high-speed railway’s construction.
Preparations are nearing completion for the launch of two 1,250-tonne Tunnel Boring Machines (TBMs) that will carve the final 4.5-mile stretch of HS2’s underground route between Old Oak Common and Euston.
The twin machines, named Karen and Madeleine, are now fully assembled beneath Old Oak Common and are undergoing final testing ahead of their expected launch in early 2026.
Once operational, they will take approximately 12 months to complete the Euston Tunnel, running at an average rate of 16 metres per day beneath west and central London.
Manufactured by Herrenknecht AG in Germany and reassembled on site by HS2’s London Tunnels contractor — the Skanska Costain STRABAG (SCS) joint venture — the 190-metre-long TBMs are designed specifically to cut through London Clay.
Each machine features a cutterhead 8.53 metres in diameter, installing pre-cast concrete segments as it moves forward to create twin tunnels with an internal diameter of 7.55 metres.
The two machines have been named in keeping with tunnelling tradition, after pioneering women in transport and engineering. Karen honours Karen Harrison, the UK’s first female train driver who worked out of Old Oak Common depot. Madeleine is named after Madeleine Nobbs, the former president of the Women’s Engineering Society.
“We welcome the commitment from the Government to build HS2 all the way to Euston, and preparations to tunnel from Old Oak Common are now well underway,” said Huw Edwards, Stations Delivery Director at HS2 Ltd.
“A terminus station for HS2 in the heart of the capital will provide a vital gateway for passengers travelling to and from the Midlands and North, and will lead the transport-led regeneration of Euston — supporting growth in the local economy and creating thousands of new homes and jobs.”
The Euston Tunnel represents a critical link in HS2’s London section, extending the high-speed line directly into central London. Once complete, the route will bring passengers closer to the city centre, improve connectivity across the country, and unlock major regeneration opportunities in and around Euston.
The tunnel construction builds on significant progress already achieved in west London. Earlier works at Atlas Road created a logistics tunnel to transport materials and remove excavated spoil, while two spray-concrete-lined launch tunnels have been completed to allow the TBMs to begin their eastward journey towards Euston.
The arrival of the line into Euston is expected to boost rail capacity, cut journey times, and stimulate economic development across the Midlands, North, and London.