HS2 Delta Junction video: A new era for high-speed rail in Birmingham

Engineers working on HS2’s complex triangular intersection outside Birmingham have successfully completed the construction of four parallel viaduct decks – an essential part of the huge project

The viaducts being built near Coleshill in Warwickshire stretch for more than 600m and form a small part of the Delta junction – a huge intersection being built to the east of Birmingham for the new high-speed railway.

Like the nearby Spaghetti Junction, the Delta is formed of a series of interconnected viaducts, flyovers and underpasses, taking the high-speed line over motorways, local roads, railways, rivers and floodplains.

The Coleshill East and West viaducts form the southern part of the junction, where the railway split apart as it crosses a local road and the floodplain of the river Cole, between the M6 and M42.

Two parallel viaduct spans will carry the four-track mainline running north and south, while two narrower viaducts on either side will carry services to and from the new Birmingham Curzon Street station in the city centre.

HS2 completes deck assembly for Coleshill viaductsplaceholder image
HS2 completes deck assembly for Coleshill viaducts | HS2

What’s been said

Caroline Warrington, HS2 Ltd’s Head of Delivery, said: “HS2 will transform journeys between our two largest cities, while freeing up space on the existing West Coast Main Line for more freight and local services.

“The Delta forms a key part of the project and it’s great to see it starting to come together. I’d like to thank everyone involved in the Coleshill viaducts and look forward to seeing more progress in the year ahead, as the focus turns to completing the robust kerbs and parapets.”

The construction of the Coleshill viaducts – which stretch for a combined total of 2.4km – is being delivered by HS2’s main works contractor in the Midlands, Balfour Beatty VINCI.

The decks are made of 1,024 individual concrete segments which were manufactured off-site at a purpose-built facility a few miles away at Kingsbury. These were then moved to site before being lifted and secured into position to form the spans of the viaducts.