Everything you need to know about ambitious Kingshurst regeneration project after 'significant step forward'

The next stage for an ambitious village centre regeneration has been given the backing of senior Solihull councillors.

A large-scale rejuvenation of central Kingshurst gained approval from planners in April 2022 with the original aim for it to be completed by 2026.

Phase one saw 25 social rented homes – a mix of three and four-bedroom – built on the site of the former Mountfort pub with residents moving in last year.

Community health and retail building proposed for Kingshurstplaceholder image
Community health and retail building proposed for Kingshurst | Solihull Council/LDRS

But phase two is set to be even more transformative with it set to include a new community, health and retail building; six new houses and a new vicarage.

The plan is for the new community building to include much needed GP provision, public health services, a library, community spaces, and retail units.

A community cafe and a convenience store run by Co-op – which already operates a village store – are also in the plans.

And it has now been revealed there is a proposal for Solihull Community Housing (SCH) to relocate from its current home at Endeavour House into the new building.

As the Local Democracy Reporting Service reported last January Solihull Council’s cabinet agreed to move forward with phase two and determine the costs of delivering it.

At the latest cabinet meeting councillors heard the authority’s construction partner, Willmott Dixon, had now come forward with a build cost for phase two.

This figure was discussed in private session but has been described as “broadly in line with expectations” by officers.

Helen Bielby, the authority’s project manager, told councillors: “There has been ongoing work since September to explore and analyse options to resolve the financial and occupancy issues (in the community building).

“It has been determined the overall size and external facade of the building will remain as per the design, which ensures there is no further planning consent needed, nor is there a requirement to go back several design stages.

“Internal changes however will be required to facilitate the needs of new tenancies within the building.

“Following an analysis of options after the Willmott Dixon cost return it was concluded there could be a relocation of Solihull Community Housing (SCH) into the building – that would provide the best option.”

Community health and retail building proposed for Kingshurstplaceholder image
Community health and retail building proposed for Kingshurst | Solihull Council/LDRS

The officer explained a total amount of £340,000 funding was needed to be approved by councillors to complete the design stage and prepare a full business case, allowing construction work to begin in 2026.

Cabinet members agreed to the funding and endorsed SCH moving to the site.

Council leader Councillor Karen Grinsell said: “I think we should all acknowledge the positive progress, a lot of good work has gone on.”

And following the meeting Councillor Ian Courts, the authority’s deputy leader and lead member for managed growth, added: “This decision is a significant step forward in creating a thriving, modern village centre for Kingshurst.

“Stage two, and in particular the delivery of the CHR building, represents by far the most complex element of the overall scheme.

“It is the linchpin that will bring multiple services under one roof and that complexity is precisely why it has taken time to get it right.”